Mornington Peninsula Freeway - Drainage Works

What we'll do and when

From Saturday 19 September 2020, we’ll install traffic barriers and begin work to move and protect drainage services on the Mornington Peninsula Freeway.

We'll carry out most of these works during the day on Saturdays between 7am and 3.30pm.

When we're working with the utility owners, some of this work may need to be completed on Saturdays between 3:30 pm and 5pm or on Sundays between 9am and 5pm and may require short outages. You may receive a notification from the responsible utility service provider to let you know of any planned outages.

What you can expect

We’ll use trucks, excavators and other machinery to complete the works. You may experience some noise and vibration. We’ll do our best to keep our construction impacts to a minimum.

We’ll keep you informed of changes to traffic conditions through road signs and traffic controllers. For more information, visit Victoria's Big Build.