Construction update

We're completing the final stages of the O'Herns Road Upgrade - click through for more images.

September 2021 construction update

We've opened all new lanes on O'Herns Road and the interchange to the Hume Freeway.

While major works are now complete, we’ll continue finishing works along O’Herns Road and around the upgraded intersections until later this year.

These works will include installing barriers, pavement and line marking, final landscaping and some traffic signal works at Koukoura Drive.

Since our last update, we’ve continued:

We’ve also opened your new shared walking and cycling path and on-road bike lanes between Redding Rise and the Hume Freeway.

Major works complete on the O’Herns Road Upgrade

We've upgraded O'Herns Road in two stages. As part of Stage 1, we upgraded the O’Herns Road and High Street

intersection with traffic lights and built on-road bike lanes to connect to nearby shared walking and cycling paths.

Stage 1 was completed in early 2019. Construction on Stage 2 of the O'Herns Road Upgrade started in September 2019.

As part of the upgrade, we built:

We've installed new traffic light at the future Koukoura Drive intersection. Finishing works on the northern side of the intersection will continue until later this year. The remaining connection will be built by Development Victoria.